Tracking Along

Monday, September 26, 2011 5:00 PM

The track in the brake run to the station as well as from the station to the bottom of the lift is installed. Our work on the footings is moving along quickly; to date we have completed 55% of the footing work.

Track and columns continue to arrive every few days. So far we have unloaded 64 trucks, and we expect over 100 more before we are finished. One of the large cranes has been set up and will be lifting steel in the next few days.

This week our focus will be the storage track and the bottom of the lift hill. The underground work at the station is underway as well, and will continue for the next week.

There are lots of new photos in the construction gallery to show you our continuing progress on the Leviathan site; enjoy!

Peter Switzer

Director, Maintenance & Construction

- Peter Switzer